NEW QUESTION # 45
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The overall project completion
  • B. The buoyancy of a successor activity
  • C. The end of that activity
  • D. The next activity

Answer: A


NEW QUESTION # 46
Time-scaled logic diagrams are

  • A. Only calculated using a computer.
  • B. Used to calculate the most probable activity duration.
  • C. The same as a pure-logic diagram.
  • D. Logic networks that are drawn to match the calendar.

Answer: D


NEW QUESTION # 47
What is the relationship depicted between Activity G and Activity H?

  • A. Start-to-start.
  • B. Finish-to-finish.
  • C. You cannot tell with the supplied information.
  • D. Finish-to-start.

Answer: A


NEW QUESTION # 48
Each of the following accurately describes total float in a schedule EXCEPT:

  • A. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
  • B. Can be positive or negative.
  • C. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  • D. The amount of time an activity can be delayed without delaying the overall project completion time.

Answer: C


NEW QUESTION # 49
The activity with the most total float is:

  • A. Activity F.
  • B. Activity D.
  • C. Activity C.
  • D. Activity I.

Answer: D


NEW QUESTION # 50
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

  • A. 8 work days
  • B. 18 work days
  • C. 7 work days
  • D. 15 workdays

Answer: A


NEW QUESTION # 51
What is the workweek period for this project?

  • A. Sunday through Saturday
  • B. Sunday through Friday
  • C. Monday through Friday
  • D. Monday through Saturday

Answer: A


NEW QUESTION # 52
Identify the minimum project duration.

  • A. 16 months.
  • B. 20 months.
  • C. 19 months.
  • D. 21 months.

Answer: B


NEW QUESTION # 53
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 37.
  • B. 42.
  • C. 36.
  • D. 40.

Answer: C


NEW QUESTION # 54
At a minimum, periodic reporting must be done at what interval?

  • A. As requested by the owner.
  • B. As specified in the contract documents.
  • C. As requested by the project manager.
  • D. Monthly.

Answer: B


NEW QUESTION # 55
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 7001.
  • B. 1000.
  • C. 2003.
  • D. 1001.

Answer: A


NEW QUESTION # 56
Why does activity 1001 have two successor activities?

  • A. Because the duration of activities 2001, 2002 and 200.f require two successors
  • B. Because the late finish of 1001 and the late start of 7001 require two successors
  • C. Because there are two defined logic paths for the work
  • D. Because the problem could not effectively work with only one successor

Answer: C


NEW QUESTION # 57
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

  • A. 2.3% (1 : 43.501).
  • B. 8.6% (1 : 11.591)
  • C. 9.1% (1 : 11.000).
  • D. 3.9% (1 : 25.708)

Answer: A


NEW QUESTION # 58
Project schedules help control all of the following EXCEPT for_____________________.

  • A. Resources
  • B. Cost
  • C. Time
  • D. Quality

Answer: D


NEW QUESTION # 59
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 255 days
  • B. 267 days
  • C. 407 days
  • D. 362 days

Answer: C


NEW QUESTION # 60
What does the narrow band at "Y" represent?

  • A. Resource limitation period.
  • B. Activity inactivity.
  • C. A rework period.
  • D. You cannot tell with the information supplied.

Answer: B


NEW QUESTION # 61
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

  • A. Total float.
  • B. Negative float.
  • C. Free float.
  • D. Interfering float.

Answer: A


NEW QUESTION # 62
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

  • A. Estimate to complete (ETC)
  • B. Budget at completion (BAC)
  • C. Budgeted cost of work performed (BCWP)
  • D. Estimate at completion (EAC)

Answer: A


NEW QUESTION # 63
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

  • A. Industry publications.
  • B. The Petrochemical Industry New Plant Task Duration Handbook.
  • C. The cost estimate for the plant prepared by your firm's estimating department.
  • D. Critical path schedules prepared by you for similar completed projects.

Answer: D


NEW QUESTION # 64
......